Report · Data centres and electricity

Data centres and the power constraint

Global demand, Irish meter data and US scenarios show why deliverable electricity matters more than announced capacity.

Cite and reuse
Industry
Electricity and Gas Utilities
Period
2018–2025 evidence · scenarios to 2030
Cited records
23
Reading time
8 min

The IEA estimates 485 TWh of global data-centre electricity use in 2025 and projects 950 TWh in 2030. This report separates measured local concentration from modeled demand and tests what the evidence means for grid access, onsite supply and investment commitments.

Executive assessment: the constraint is local delivery

Data centres are becoming a materially larger electricity customer, but their growth does not translate into a uniform shortage across electricity systems. The planning problem is concentrated demand arriving at particular substations, with uncertain commissioning dates and equipment requirements. A global demand forecast cannot establish whether a specific site can obtain reliable power on schedule.

Three evidence sets frame the issue. The IEA estimates worldwide data-centre electricity consumption at 485 TWh in 2025. Ireland's administrative records put the sector at 23% of mains-network metered consumption that year. Berkeley Lab's older US study presents a wide scenario range for 2028. These answer different questions: global scale, local concentration and sensitivity to technology assumptions. 1 12 15 16

Our assessment is that procurement and system planning should prioritise deliverable connections, phased load commitments and responsibility for unused infrastructure. Headline investment announcements and nominal generating capacity provide weaker evidence of when computing capacity will become operational.

Global outlook: strong growth, with an explicit forecast boundary

The IEA's April 2026 assessment puts annual data-centre electricity use at 485 TWh in 2025 and about 950 TWh in its central projection for 2030. The latter represents around 3% of global electricity demand. The outlook is an energy-consumption projection, not a pipeline of approved projects. The chart deliberately shows only the two directly supported endpoints; it does not invent annual observations between them. 1 2 3

All data-centre electricity use grew by an estimated 17% in 2025, while the AI-focused subset grew by 50%. These overlapping populations cannot be added together. Nor does the faster subset growth establish that every additional unit of sector electricity was consumed by AI. 4 5

The investment implication is conditional. Greater computing demand can coexist with improving efficiency per task. A procurement case therefore needs explicit assumptions about workload volumes, model complexity, utilisation and facility overhead. Extrapolating either a single query's electricity use or a company's total capital expenditure into sector demand would conceal those assumptions.

Global data-centre electricity: baseline and central projection

IEA April 2026 vintage; all data centres, including non-AI workloads

2 entries

Forecast Estimate Latest available period per row; periods differ

Global data-centre electricity: baseline and central projectionGlobal data-centre electricity: baseline and central projection. 2 categories, highest is 2030 projection at 950 TWh. Bars refer to different periods; each is labelled with its own. 2030 projection 2030-01-01 to 2030-12-31 2025 estimate 2025-01-01 to 2025-12-31 950 TWh 485 TWh
Global data-centre electricity: baseline and central projectionGlobal data-centre electricity: baseline and central projection. 2 categories, highest is 2030 projection at 950 TWh. Bars refer to different periods; each is labelled with its own. 2030 projection 2030-01-01 to 2030-12-31 2025 estimate 2025-01-01 to 2025-12-31 950 TWh 485 TWh
Global data-centre electricity: baseline and central projectionGlobal data-centre electricity: baseline and central projection. 2 categories, highest is 2030 projection at 950 TWh. Bars refer to different periods; each is labelled with its own. 2030 projection 2030-01-01 to 2030-12-31 2025 estimate 2025-01-01 to 2025-12-31 950 TWh 485 TWh
View the underlying data
Global data-centre electricity: baseline and central projection
Category Period Source Type Value
2025 estimate 2025-01-01 to 2025-12-31 IEA Estimate 485 TWh
2030 projection 2030-01-01 to 2030-12-31 IEA Forecast 950 TWh
Source: IEA · TWh · CC BY 4.0 · statorigin.org

Two endpoints, not an annual time series. The 2030 value is a central projection and has not occurred.

Ireland: metered evidence of concentration

Ireland provides a useful local-system case because its statistical office publishes annual meter-based consumption. In the July 2026 release, data-centre electricity rose from 3,030 GWh in 2020 to 7,663 GWh in 2025, with increases in every intervening year. The latest figure represented 23% of total metered consumption. This is a concentration measure for Ireland, not a global benchmark or a measure of AI's share. 6 11 12

The chart uses the complete recent annual sequence from one release vintage. That choice matters: the 2023 and 2024 values in this release are 6,339 and 6,973 GWh. Mixing older releases with this edition could introduce revisions that look like economic changes. 9 10

Metered consumption still has boundaries. CSO identifies relevant meters through customer activity, operator names and other checks; the administrative source does not carry a ready-made data-centre classification. Sites may enter the identified population as consumption grows. These records also do not establish the split between AI and conventional computing, or the quantity of electricity generated behind a site's meter. CSO background notes

Ireland: six years of metered data-centre electricity

CSO July 2026 release; the same statistical vintage for every year

Latest available period per row; periods differ

Ireland: six years of metered data-centre electricityIreland: six years of metered data-centre electricity. 6 categories, highest is 2025 at 7,663 GWh. Bars refer to different periods; each is labelled with its own. 2025 2025-01-01 to 2025-12-31 2024 2024-01-01 to 2024-12-31 2023 2023-01-01 to 2023-12-31 2022 2022-01-01 to 2022-12-31 2021 2021-01-01 to 2021-12-31 2020 2020-01-01 to 2020-12-31 7,663 GWh 6,973 GWh 6,339 GWh 5,273 GWh 4,012 GWh 3,030 GWh
Ireland: six years of metered data-centre electricityIreland: six years of metered data-centre electricity. 6 categories, highest is 2025 at 7,663 GWh. Bars refer to different periods; each is labelled with its own. 2025 2025-01-01 to 2025-12-31 2024 2024-01-01 to 2024-12-31 2023 2023-01-01 to 2023-12-31 2022 2022-01-01 to 2022-12-31 2021 2021-01-01 to 2021-12-31 2020 2020-01-01 to 2020-12-31 7,663 GWh 6,973 GWh 6,339 GWh 5,273 GWh 4,012 GWh 3,030 GWh
Ireland: six years of metered data-centre electricityIreland: six years of metered data-centre electricity. 6 categories, highest is 2025 at 7,663 GWh. Bars refer to different periods; each is labelled with its own. 2025 2025-01-01 to 2025-12-31 2024 2024-01-01 to 2024-12-31 2023 2023-01-01 to 2023-12-31 2022 2022-01-01 to 2022-12-31 2021 2021-01-01 to 2021-12-31 2020 2020-01-01 to 2020-12-31 7,663 GWh 6,973 GWh 6,339 GWh 5,273 GWh 4,012 GWh 3,030 GWh
View the underlying data
Ireland: six years of metered data-centre electricity
Category Period Source Type Value
2020 2020-01-01 to 2020-12-31 CSO Actual 3,030 GWh
2021 2021-01-01 to 2021-12-31 CSO Actual 4,012 GWh
2022 2022-01-01 to 2022-12-31 CSO Actual 5,273 GWh
2023 2023-01-01 to 2023-12-31 CSO Actual 6,339 GWh
2024 2024-01-01 to 2024-12-31 CSO Actual 6,973 GWh
2025 2025-01-01 to 2025-12-31 CSO Actual 7,663 GWh
Source: CSO · GWh · CC BY 4.0 · statorigin.org

Mains-network metered consumption. All years are subject to revision; onsite generation and AI-only workloads are not separately measured.

United States: a scenario range is not a point forecast

Berkeley Lab's December 2024 study estimated US data-centre electricity use at about 76 TWh in 2018 and 176 TWh in 2023. Its 2028 scenarios span roughly 325–580 TWh. This edition predates the IEA's 2026 update and is retained as a clearly dated national sensitivity analysis, not presented as a newly issued September 2026 forecast. 13 14 15 16

The study models equipment stocks and operating practices, including cooling, rather than summing a comprehensive census of electricity meters. Its forward range depends on assumptions about equipment shipments, how intensively accelerated servers operate and facility efficiency. The endpoints are scenarios, not statistical confidence limits. Berkeley Lab, executive summary

For planning, the value of this range is the question it forces: which commitments remain viable across different levels of realised demand? A utility's proposed reinforcement should be assessed against customer milestones and downside utilisation as well as an aggregate growth narrative. Subtracting this older US projection from the newer global projection would not produce a defensible rest-of-world forecast.

US electricity demand: historical estimates and future endpoints

LBNL December 2024 vintage; 2028 bars bound one scenario range

Forecast Estimate Latest available period per row; periods differ

US electricity demand: historical estimates and future endpointsUS electricity demand: historical estimates and future endpoints. 4 categories, highest is 2028 high scenario at 580 TWh. Bars refer to different periods; each is labelled with its own. 2028 high scenario 2028-01-01 to 2028-12-31 2028 low scenario 2028-01-01 to 2028-12-31 2023 estimate 2023-01-01 to 2023-12-31 2018 estimate 2018-01-01 to 2018-12-31 580 TWh 325 TWh 176 TWh 76 TWh
US electricity demand: historical estimates and future endpointsUS electricity demand: historical estimates and future endpoints. 4 categories, highest is 2028 high scenario at 580 TWh. Bars refer to different periods; each is labelled with its own. 2028 high scenario 2028-01-01 to 2028-12-31 2028 low scenario 2028-01-01 to 2028-12-31 2023 estimate 2023-01-01 to 2023-12-31 2018 estimate 2018-01-01 to 2018-12-31 580 TWh 325 TWh 176 TWh 76 TWh
US electricity demand: historical estimates and future endpointsUS electricity demand: historical estimates and future endpoints. 4 categories, highest is 2028 high scenario at 580 TWh. Bars refer to different periods; each is labelled with its own. 2028 high scenario 2028-01-01 to 2028-12-31 2028 low scenario 2028-01-01 to 2028-12-31 2023 estimate 2023-01-01 to 2023-12-31 2018 estimate 2018-01-01 to 2018-12-31 580 TWh 325 TWh 176 TWh 76 TWh
View the underlying data
US electricity demand: historical estimates and future endpoints
Category Period Source Type Value
2018 estimate 2018-01-01 to 2018-12-31 Berkeley Lab Estimate 76 TWh
2023 estimate 2023-01-01 to 2023-12-31 Berkeley Lab Estimate 176 TWh
2028 low scenario 2028-01-01 to 2028-12-31 Berkeley Lab Forecast 325 TWh
2028 high scenario 2028-01-01 to 2028-12-31 Berkeley Lab Forecast 580 TWh
Source: Berkeley Lab · TWh · CC BY 4.0 · statorigin.org

The two 2028 bars are alternative endpoints, not additive demand. All values come from the same older model vintage.

Power, energy and reliability require separate assessments

Annual consumption in TWh describes energy over time. Capacity in GW describes power at an instant. Converting a planned connection into annual electricity demand requires assumptions about utilisation and the timing of the ramp. The same distinction applies to batteries: their power rating does not reveal how many hours they can sustain a load.

The IEA projects approximately 20–25 GW of battery storage at data centres globally by 2030, and around 15–27 GW of onsite gas generation powering data centres, mostly in the United States. These ranges describe different technologies and functions. They should not be added and labelled firm data-centre supply. 17 18 19 20

Its engineering analysis also finds that reliably supplying critical, variable loads with onsite gas can require generation infrastructure 30–70% above demand. This is a design requirement under the analysis, not an observed fleet-wide overbuild rate. 21 22

A credible project assessment should therefore separate continuous energy supply, short-duration load smoothing, contingency reserves and grid access. A battery can address a rapid fluctuation without solving a prolonged energy deficit; redundant generating capacity can improve resilience while increasing capital and maintenance requirements.

Infrastructure assessments with distinct functions
Measure Value Unit Period Region Basis Source
2030 battery power: lower endpoint 20 GW 2030-01-01 to 2030-12-31 Global forecast IEA
2030 battery power: upper endpoint 25 GW 2030-01-01 to 2030-12-31 Global forecast IEA
2030 onsite gas: lower endpoint 15 GW 2030-01-01 to 2030-12-31 Global forecast IEA
2030 onsite gas: upper endpoint 27 GW 2030-01-01 to 2030-12-31 Global forecast IEA
Generation redundancy: lower assessment 30 percent 2026-04-16 Global estimate IEA
Generation redundancy: upper assessment 70 percent 2026-04-16 Global estimate IEA
Range endpoints are alternatives, not additive capacity. Battery power is not stored energy. Redundancy assessments are not observed fleet overbuild.

The September grid update changes the available response

The IEA's 17 September 2026 grid report adds a useful qualification to the debate: infrastructure expansion and better operation of existing networks can proceed together. It estimates that selected grid technologies could enable up to 330 GW of additional generation, storage and demand connections without reinforcement. This is system-wide technical potential, not spare capacity reserved for data centres. 23

The technologies assessed include dynamic equipment ratings, changes to network configuration and control of power flows. Their relevance to a particular site depends on weather, network conditions and reliability constraints. Their potential therefore cannot be allocated to proposed projects simply in proportion to requested capacity. IEA grid assessment

Our operational inference is to evaluate an alternative connection package alongside the conventional expansion plan: staged energisation, an agreed curtailment envelope, network-control improvements and verified onsite flexibility. Each option should state the service it actually supplies and the circumstances in which it becomes unavailable. That creates a basis for comparing earlier access against cost and operational restrictions.

A decision framework for developers, utilities and policymakers

The evidence supports a milestone-based approach to demand rather than treating every announced project as inevitable load. Developers should demonstrate how power becomes available as computing equipment is installed. Utilities should connect reinforcement commitments to credible customer delivery schedules. Policymakers should make the allocation of upgrade and stranded-asset costs explicit.

For an individual project, request four linked disclosures:

  • The connection agreement, energisation stages and conditions for firm or interruptible service.
  • A load ramp tied to equipment installation and contracted workloads, with downside and delay cases.
  • The complete supply design, distinguishing energy purchases, onsite generation, battery power and battery duration.
  • The tariff and financial commitments that determine who pays if contracted demand fails to materialise.

These are analytical recommendations, not a claim that the cited agencies prescribe one standard contract. The central test is whether demand, infrastructure and financial commitments become binding on compatible timelines. A larger headline pipeline alone cannot answer that question.

Methodology, scope and limitations

Research closes on 22 September 2026. The global demand baseline and projections come from the IEA's April 2026 assessment; grid context uses its September 2026 publication. Irish figures are the July 2026 CSO release. US figures retain the December 2024 Berkeley Lab vintage. Publication date and data period are recorded separately for each source and statistic.

Historical IEA and Berkeley Lab model outputs are classified as estimates. Irish administrative observations are classified as actuals while retaining CSO's revision caveat. Future scenario endpoints are classified as forecasts; engineering requirements and technical potential are assessments, not observed deployment. No chart combines national meter data with global modeled data, and none converts GW to TWh without an operating assumption.

The CSO page contains an inconsistent year in one release header. We use 7 July 2026, corroborated by its release landing page and statistician's dated statement, while preserving the fetched page unchanged. Release landing page

The report does not estimate AI-only electricity levels, water use, emissions or project-level electricity prices. Those require different boundaries and additional evidence. IEA and CSO figures are adapted and attributed under CC BY 4.0; charts and interpretation are StatOrigin's, without agency endorsement. Author: StatOrigin editorial / AI-assisted research.

Data behind this report

The industry hubs and indicator series these figures come from. Each page carries the full table, every source and the records this report does not quote.

Sources

Every figure in this report is a published StatOrigin record. The table lists the 23 cited statistics. Sort any column or download CSV. Open a record for APA, MLA, Chicago or BibTeX.

Cited statistics in this report
Figure Indicator Region Value Period Basis Source Record
Global data centre electricity consumption, IEA April 2026 vintage Global data centre electricity consumption, IEA April 2026 vintage Global 485 TWh 2025 estimate IEA STO-862351D40C-99EE102F4C-A5E8
Global data centre electricity consumption, IEA April 2026 vintage Global data centre electricity consumption, IEA April 2026 vintage Global 950 TWh 2030 forecast IEA STO-9C4DF6787F-12EEC23FEB-CEDC
Data centres as a share of global electricity demand, IEA 2026 Data centres as a share of global electricity demand, IEA 2026 Global 3% 2030 forecast IEA STO-CB6D102DD7-A7356EB4A7-9835
All data centres: annual electricity consumption growth All data centres: annual electricity consumption growth Global 17% 2025 estimate IEA STO-FA7C23A210-B1F4C13B27-0EA9
AI-focused data centres: annual electricity consumption growth AI-focused data centres: annual electricity consumption growth Global 50% 2025 estimate IEA STO-B1459ACFB5-FB44A01821-E01E
Ireland: metered electricity consumption by data centres Ireland: metered electricity consumption by data centres Ireland 3,030 GWh 2020 actual CSO STO-0B1EAAA58E-C852B74A4A-1A60
Ireland: metered electricity consumption by data centres Ireland: metered electricity consumption by data centres Ireland 4,012 GWh 2021 actual CSO STO-49E6484576-3A490CDB5A-52D6
Ireland: metered electricity consumption by data centres Ireland: metered electricity consumption by data centres Ireland 5,273 GWh 2022 actual CSO STO-ED9D90760D-3DCF0769FF-3BF9
Ireland: metered electricity consumption by data centres Ireland: metered electricity consumption by data centres Ireland 6,339 GWh 2023 actual CSO STO-78C846E30F-BFE7B1ED99-C4E8
Ireland: metered electricity consumption by data centres Ireland: metered electricity consumption by data centres Ireland 6,973 GWh 2024 actual CSO STO-3C32DFBE3D-FA09C6B250-28D2
Ireland: metered electricity consumption by data centres Ireland: metered electricity consumption by data centres Ireland 7,663 GWh 2025 actual CSO STO-CBC3C738B6-E8516AD1E3-65A5
Ireland: data centres share of metered electricity Ireland: data centres share of metered electricity Ireland 23% 2025 actual CSO STO-CCFCDA28BC-0320DA5761-8F43
US data centre electricity consumption, LBNL December 2024 vintage US data centre electricity consumption, LBNL December 2024 vintage United States 76 TWh 2018 estimate Berkeley Lab STO-2EDBB0B5E3-B566B28950-28D7
US data centre electricity consumption, LBNL December 2024 vintage US data centre electricity consumption, LBNL December 2024 vintage United States 176 TWh 2023 estimate Berkeley Lab STO-0927D153DD-90B124F7C1-252C
US data centre electricity consumption: low scenario endpoint US data centre electricity consumption: low scenario endpoint United States 325 TWh 2028 forecast Berkeley Lab STO-A52538F02E-747C0BC3AC-8CC4
US data centre electricity consumption: high scenario endpoint US data centre electricity consumption: high scenario endpoint United States 580 TWh 2028 forecast Berkeley Lab STO-08D16E7E52-34EF67CD9B-C0D9
Data-centre battery storage power: lower projection endpoint Data-centre battery storage power: lower projection endpoint Global 20 GW 2030 forecast IEA STO-C55485D909-7C5C114F37-FF59
Data-centre battery storage power: upper projection endpoint Data-centre battery storage power: upper projection endpoint Global 25 GW 2030 forecast IEA STO-0F049DD21B-E43B9E9234-BB7C
Onsite gas generation for data centres: lower projection endpoint Onsite gas generation for data centres: lower projection endpoint Global 15 GW 2030 forecast IEA STO-035C7CD80F-36F99F82F9-89CE
Onsite gas generation for data centres: upper projection endpoint Onsite gas generation for data centres: upper projection endpoint Global 27 GW 2030 forecast IEA STO-AA2AF86402-72675B5ACE-C2C0
Onsite gas generation overbuild relative to data-centre demand: low endpoint Onsite gas generation overbuild relative to data-centre demand: low endpoint Global 30% as of 16 Apr 2026 estimate IEA STO-0094BDC25A-CB489B5C6E-26CE
Onsite gas generation overbuild relative to data-centre demand: high endpoint Onsite gas generation overbuild relative to data-centre demand: high endpoint Global 70% as of 16 Apr 2026 estimate IEA STO-DB9D53577C-EB8E793BF0-C781
Additional connections enabled by selected grid technologies: upper potential Additional connections enabled by selected grid technologies: upper potential Global 330 GW as of 17 Sep 2026 estimate IEA STO-5A921D587E-51A00D4D06-9167

Cite this report

StatOrigin. (2026). Data centres and the power constraint. https://statorigin.org/reports/data-centres-power-constraint-2026

Prefer citing the underlying statistic when you only need one figure. Published 22 September 2026 . Data licence: CC BY 4.0.